Ness Point

Woodberry Down, Hackney

Working as civil engineering designers for the project in a framework agreement with the partnering team. MLM designed the civil engineering works including major temporary and permanent works and detailing of the architectural element of the project. £7m scheme for screening, grit extraction and pumping station for raw
sewage.

Key Features

8m deep excavations requiring temporary sheet piling and dewatering measures

Give full consideration to contamination issues required due to high grade waste and a gas works on the adjacent site

The works constructed on the site of an existing sewage pumping station, repairing extensions, preliminary service diversion work and phasing of the permanent works

Water and Public Health Projects